The Dana Point Harbor Concept Plan is continually refined, based on input from merchants, boat owners, homeowners and other key community leaders
Refined plan is introduced to general public for continued refinement
2003
The refined concept plan, which reflects the Task Force's original Plan Priorities as well as the input of today's community leaders and residents, will be presented to the Orange County Board of Supervisors for approval
County will develop a Dana Point Harbor Master Plan
The plan will undergo final design
Project Dimensions, Inc. has been selected by the Board of Supervisors to oversee the revitalization master plan as the contract administrator and project manager
RBF Consulting begins developing the Environmental Impact Report for the project
A.C. Martin, Inc. has been selected as the Architectural / Engineering firm to complete the design, permitting and construction of the Dana Point Harbor concept master plan for revitalization
2005
Draft Environmental Impact Report ready for public review
Orange County Planning Commission recommends certification of the Environmental Impact Report
2006
Orange County Board of Supervisors certifies the Environmental Impact Report and approves the Revitalization Plan
City of Dana Point approves the Dana Point Harbor Revitalization Plan and District Regulations
Submitted Local Coastal Program Amendment to the California Coastal Commission
Launch ramp renovation begins
2007
Work with the California Coastal Commission on processing the Local Costal Program Amendment (LCPA)
Begin Draft of Subsequent Environmental Impact Report (SEIR) for Waterside portion of the Revitalization Project
Launch Ramp renovation completed on time and on budget
2008
Harbor dredging begins
Worked with the California Coastal Commission on public hearing schedule for Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase
2009
California Coastal Commission Approval of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase
2010
City of Dana Point Harbor public hearing and unanimous approval of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase
Final certification of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase by California Coastal Commission
2011
Public hearing for Local Costal Program Amendment (LCPA) - Implementation Plan (IP)
Finalize Draft Subsequent Environmental Impact Report (SEIR) for Phase II for public review
2012
Finalize Coastal Development Planning process for Phase I
Finalize Subsequent Environmental Impact Report (SEIR) for Phase II
2013
Phase I - construction begins Coastal Development Planning process for Phase I
2014
Phase II - Construction begins
You Are Now Leaving the County of Orange Official Portal
The policies that apply to the County of Orange Official Web Portal may not be the same as the terms of use for other web sites. The County of Orange cannot attest to the accuracy of the information provided by the linked websites. Any link to an external website is not intended as an endorsement of that external website, any product or service offered or referenced to or any views that might be expressed or referenced therein.